DAY 3 !
Posted 18 May 2022 15:44
DAY 3 | DESIGN DEVELOPMENT AND CONSULTATION

Today we finalised the design of the exhibition and updated Stephen with the development. We then split everyone into themes for the poster designs.
Posted 18 May 2022 15:46
DAY 3 ACTIVITY!

Today the groups finalised their individual designs, and gave a presentation. We then chose the most appropriate proposal to move forward with, the chosen proposal was then developed as a team.
We then had a meeting online with Stephen updating him with the final exhibition design. We ended the day with preparing everyone with what to add Onto the exhibition posters by splitting them into themes.
Posted 18 May 2022 15:47
MEET THE REST OF THE TEAM!

Posted 18 May 2022 15:50
DAY 9!
Posted 26 May 2022 23:51
DAY 9 | PUTTING UP THE ROOF

Today we finished the roof and secured the partition walls.
Posted 27 May 2022 18:50
DAY 9 ACTIVITY!

We began the day by assembling one of the last walls, we had to extend the wall by using spare pieces of wood. We then began constructing the roof frame by adding the beams on either wall, after we added the central beams and secured them. The other half of the group worked on securing the partition walls to the exhibition. Some of the group also collected flowers to add to the allotment plots and willow arch. After the frame was secure we placed the corrugated plastic sheets as the lightweight roof on either side of the walls. As we did not have any corrugated plastic left we used a red vinyl sheet to cover the back centre of the exhibition to provide more covering. We then cleared the site ready for the exhibition
Posted 27 May 2022 18:51